Mariner East 2 Pipeline Completion Delayed Again

Nov 9, 2017

Sunoco Pipeline’s parent company, Energy Transfer Partners, said Wednesday that its Mariner East 2 pipeline will be put into service in the second quarter of 2018, some 18 months later than originally planned, because of delays caused by Pennsylvania regulators.

Chief Financial Officer Tom Long said during the company’s third-quarter earnings call that the project has been held up in part by the Public Utility Commission’s recent ban on horizontal directional drilling at a location in Chester County’s West Goshen Township until the PUC hears a dispute between the township and Sunoco over the siting of a valve. The hearing is scheduled for April next year. 